Latest update, to answer questions from friends.
Ground floor (1-4), drywall is nearly finished, a little more sanding and it will be ready for paint, probably next week. Then the floor will get coated and the posts will get boxed in, lights installed, etc.
Second floor (5-6) - plan is to get the library done first, so I can start moving in bookshelves, books, cabinets, etc. With minor details to be completed that should start tomorrow night.
Office still needs some work (7) its currently the staging area for the library. It will be the focus next week, contractors assure me it will not take long.
Third floor (8) - we have pre-staged books that were shipped home into the storage area (about one ton) so that they can simply be moved downstairs once the additional bookcases are in. Still seven large bookshelves in the old office to be emptied and moved.
In addition, before the kids went back to college (slave labor) we pre-staged some of the collection into the garage (9-10), putting about 1/3rd of the collection over half way to its new home.
Getting close, moving fast, but still a long way to go.